The Rosemont Building, 410-428 Sauchiehall Street, Glasgow – Refurbishment Project Update: Restoration Progress June 2025 – February 2026
At Redpath Bruce, we are proud to coordinate high-quality property restoration and building repair projects across Scotland. The refurbishment has been a significant programme of works, combining traditional stonemasonry, roofing upgrades, structural repairs and internal improvements.
Below is a detailed progress update covering the project journey from June 2025 through February 2026, highlighting key milestones, conservation work and the final stages of completion.
Project Commencement – June 2025
The project officially commenced on site following a progress meeting on 19th June 2025. Full scaffolding was installed to the front and rear elevations to enable safe access and public protection while works progressed.
Key early activities included:
- Front elevation cleaning works
- Rear elevation cleaning
- Roof stripping began on 16th June
- Chimney inspections and preparation for repairs
- Removal of aerials and historic glazed roof sections
- Installation of site welfare facilities
Initial surveys confirmed no asbestos risks, and attic inspections were scheduled following temporary lighting installation. These early steps ensured a safe and well-managed start to the restoration programme.
Roof and Stonework Progress – July 2025
July saw major structural progress, with:
- Full roof stripping completed (excluding the mansard)
- New roofing felt installed
- Rot discovered at rear eaves leading to further investigation
- Lime pointing samples agreed for conservation works
- Cement mortar removal continuing across elevations
Detailed stone surveys were completed to the front elevation, and chimney repair works advanced significantly, preparing the building for long-term durability.
Structural Repairs and Chimney Completion – August 2025
During August, the focus shifted to deeper structural repairs:
- Over 20 rafter and joist ends identified for replacement
- Attic clearance and insulation removal completed
- Multiple chimneys fully repaired and signed off
- Rear elevation mortar removal completed
- Front elevation stone indents ordered
Scaffold reconfiguration allowed safe access for parapet repairs and future slating works.
Repointing and Leadwork – September 2025
By September, significant restoration milestones had been reached:
- Chimney repairs completed and approved
- Rear elevation lime repointing reached approximately 50%
- Cement mortar removal progressed at the front elevation
- New lead cloak detailing installed to roof areas
Weather protection remained in place while attic works paused temporarily until the roof was watertight.
Stone Repairs and Roof Preparation – October 2025
October marked strong visible transformation across the building:
- Front elevation cement mortar removal completed
- Approved pointing samples implemented
- Stone repairs progressed systematically
- Rear elevation repointing completed
Roof works on the rear slope neared completion, with front slope leadwork reaching 95% ahead of slating scheduled for early November.
Finishing Stages Begin – November 2025
The project moved into finishing phases with:
- Mid-level stone repairs progressing
- Grant-assisted window replacement discussions underway
- Roof slating nearing completion
- Common close ceiling and plaster repairs finished
Rot repairs in upper floor flats advanced significantly, works were completed and handed back to the owner.
Front Elevation Transformation – December 2025
December saw continued advancement across external works:
- Natural stone pillars prepared off-site
- Higher-level repointing underway
- Rear elevation works largely completed aside from snagging
- Attic insulation installation began
Front roof slating and leadwork were nearly finished ahead of the holiday period.
Major Milestones Achieved – January 2026
As the new year began, progress accelerated toward completion:
- Rear elevation fully signed off
- New stone cills and columns installed
- Roof slating completed to front slopes and dormers
- New safety anchors and communal aerial installed
Decoration works commenced within the common close, alongside proposals for improved stair lighting.
Final Stages and Project Close-Out – February 2026
The project has now entered its final phase:
- Rear scaffolding fully removed
- Front elevation stone repairs nearing completion
- Pointing works approximately 95% complete
- Mansard roof works fully signed off
Additional finishing works include:
- Installation of new common close lighting
- Final attic insulation sections
- Window works and stairwell decoration
- Drone photography capturing completed roof and rear elevation
Rot repairs progressed to final framing and sheeting, with sign-off expected imminently.
Redpath Bruce: Coordinating High-Quality Property Restoration
The project demonstrates commitment to:
- Traditional stone restoration and lime pointing
- Roof and chimney conservation
- Structural repair solutions
- High-quality project coordination
From initial scaffold installation to the final finishing details, this project highlights our expertise in coordinating complex refurbishment works.
Looking Ahead
With the project now approaching completion, only minor snagging and finishing works remain. Wiseman Associates will continue to ensure a smooth close-out phase for all stakeholders.
